MS 52 Project Management
Note: Please attempt all the questions and send it to the Coordinator of the study
center you are attached with
1) Describe the important phases of a project life cycle.
2) Discuss the various methods of financial evaluation of the projects. Make a comparative analysis of these methods.
3) What are the different organization structures recommended for project organization and what are their advantages and disadvantages?
4) Explain the use and advantages of squared networks in Project Management with the help of an example.
5) Draw the project diagram from the information given below. Also identify the critical path and determine the project completion time.
Task A B C D E F G H I J K L M
Precedence - A B B D D E,F G G H,I C K J,L
Time (Hours) 16 11 14 9 12 10 30 19 11 7 40 9 14